docs: AUDIT_TRAIL_PRD — production-readiness gate for staffing client
J flagged that smoke + parity tests prove the surface compiles, NOT that an audit response can be produced for a specific person — and the staffing client won't sign without defensible discrimination-claim response capability. New docs/AUDIT_TRAIL_PRD.md captures: - worked example: John Martinez at Warehouse B requests audit - subject audit response output format (per-decision row schema) - surface map: where decisions happen today, where the gaps are - PII handling rules (tokenization, protected-attribute exclusion, inferred-attribute risk) - identity service design intent (separate daemon, audited reads) - retention + right-to-be-forgotten policy intent - 9-phase implementation sequence with explicit per-phase exit criteria - cross-runtime requirement (both Rust + Go must satisfy) - 7 open questions blocking phase 2+ that need J's call STATE_OF_PLAY + PRD updated with explicit "production-ready blocker" section pointing at the new doc. The "substrate is shipped" framing gets a caveat: substrate ≠ production-ready until audit phase 9 exits. No code changes. This is the planning artifact J asked for before we start building. Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com>
This commit is contained in:
+12
@@ -161,6 +161,18 @@ The feedback signal is **statistical + semantic**, not neural. No model training
|
||||
|
||||
---
|
||||
|
||||
## Production-readiness blocker (2026-05-03)
|
||||
|
||||
Substrate is mostly shipped through Phase 45. Throughput, parity, and observability are all measured.
|
||||
|
||||
**The production-readiness gate is the audit trail.** Staffing client requires defensible response to discrimination claims (worked example: John Martinez at Warehouse B requests every AI-system decision affecting him). PII tokenization, subject-of-record query, retention SLA, and right-to-be-forgotten under append-only logs are NOT YET BUILT.
|
||||
|
||||
Authoritative document: **`docs/AUDIT_TRAIL_PRD.md`**. 9-phase implementation plan, current-state-vs-target gap table, open questions blocking phase 1.
|
||||
|
||||
Until the audit-trail PRD's phase 9 exit criterion is met, "production-ready" claims are aspirational. Internal substrate (Lance, observability parity, cross-runtime fabric) is solid; subject-audit story is not.
|
||||
|
||||
---
|
||||
|
||||
## Phases
|
||||
|
||||
### Phase 0-5: Foundation ✅ COMPLETE
|
||||
|
||||
Reference in New Issue